Louisiana: Who Pays If Meta Leaves Early?

Entergy’s gas plants for Meta’s Richland Parish data center could last 30 years. The power deal may not. What happens to the bill if Meta walks?

By Lynn Matthews - November 23, 2026
 Louisiana: Who Pays If Meta Leaves Early?
Image Credit: K on Pexels

Across the country, companies are racing to build the data centers that run artificial intelligence, and those buildings use enormous amounts of electricity. In north Louisiana, one project shows how that demand can reach everyday households.

Entergy Louisiana has asked state regulators to approve seven new gas plants to serve Meta's data center in Richland Parish, on top of three announced earlier. A vote is expected in December, and who pays if the project changes is a question every community will face as AI moves in.

The future of American AI will depend partly on whether communities trust the deals that bring these buildings to town.

The left wants to slow the buildout

Sen. Bernie Sanders and Rep. Alexandria Ocasio-Cortez announced the AI Data Center Moratorium Act on March 25. It would halt construction and expansion of AI data centers until national safeguards are in place, including a guarantee that AI does not raise electricity or utility prices. Its stated aim is to "slow down the development of AI to give democracy a chance to catch up."

Voters have already shown where many of them stand. Of 41 local data center measures on this year's midterm ballots, voters sided against the industry in 40. A March Gallup poll found 71% of Americans opposed a data center in their area.

Democrats do not agree on what to do about it. New York Gov. Kathy Hochul froze permits for new hyperscale data centers for up to a year, while other Democrats favor hearings, bipartisan bills, and rules that make data centers pay for the grid upgrades they require. Building trades unions see jobs in the buildout, which complicates any ban.

A test case in Richland Parish

Meta's data center in Richland Parish comes with a very large power plan. Entergy's plan includes 10 gas plants with a combined 5.2 gigawatts of capacity, along with 2.5 gigawatts of new solar power. Three were announced earlier, and the seven new plants still need a vote from the Public Service Commission. Entergy's CEO has said the data center will use 4,500 megawatts, about four times New Orleans' power use.

Meta says Entergy's other customers will not pay for its power through what it calls a Ratepayer Protection Pledge. It has also promised money for community projects, bill assistance, and home energy efficiency, though critics call those commitments non-binding. Entergy projects $2.65 billion in customer benefits over 20 years, mainly by offsetting fixed grid costs such as storm recovery, and CEO Phillip May has said the deal balances growth with affordable rates.

On Nov. 18, residents marched in downtown Baton Rouge and rallied outside a Public Service Commission meeting, urging regulators to reject the plan. The open question is what happens if the project does not run its full course.

What the contract says

The original power agreement runs 15 years and can be extended three times for five years each, up to 30 years in all, according to a filing in the Public Service Commission docket that quotes Entergy's own statements. The gas plants are expected to operate about 30 years, which is longer than the original term. Testimony on the expansion refers to a 20-year contract, and three of the new plants would be depreciated over 32 years.

Entergy says the agreement sets termination fees and collateral, and that early-termination payments are backed in part by a parent guaranty from Meta and by credit insurance. Entergy executive Larry Hand has called the contract "irrevocable" and said Meta must provide a payment guarantee once the data center is finished or it does not receive electricity. Entergy CEO Phillip May says the contract requires Meta to pay for its power even if it leaves early.

Where critics see a gap

Consumer and environmental groups that asked regulators to investigate the deal argue that the protections may not cover everything. They say Meta's liability under the parent guaranty is capped, and the filing does not state the amount. Meta has also sold an 80% stake in the data center to Blue Owl Capital, and the groups say it is unclear whether Entergy's termination payments would rank ahead of investors' payments if the project were sold.

They also point out that Meta leases the data center in four-year terms, which would let it exit as early as 2033. Public Service Commissioner Davante Lewis has warned that households could be left with the remaining plant costs if Meta leaves early. The commission voted 4-1 not to open a formal probe into the ownership change.

None of this means Meta intends to leave. Sierra Club says much of Entergy's analysis is shielded from public view under nondisclosure agreements, so the answer depends on terms the public has not seen. Entergy is also seeking about $237 million in property tax relief, which critics say shifts costs to taxpayers as well as ratepayers.

What a fair deal could look like

The question reaches well past Louisiana. Cornell researchers estimate that data center operators pay for only about 38% of the infrastructure costs tied to their growth, and state utility regulators can require data centers to cover the grid upgrades they need. Microsoft has pledged to pay its own power costs, so the idea is within reach.

For a project like Meta's, communities and regulators could ask for protections such as these (they are options, not terms confirmed in any filing):

•       A contract term that matches the payoff period of the plants built to serve the project

•       A termination payment, due on exit, that covers the unpaid cost of those plants

•       Collateral, such as a letter of credit or a parent company guaranty, sized to the unpaid balance without a cap

•       Public disclosure of the guaranty amount and the order in which creditors would be paid

What comes next

The stakes are large. The four biggest cloud companies expect to spend $720 billion to $740 billion on capital projects in 2026, and ING estimates that AI-related investment accounts for 37% of U.S. economic growth. Slowing that investment carries a cost, and so does losing public trust in it.

Where the next data centers go will depend heavily on power. The communities that win them will likely be the ones that can supply electricity quickly and show their residents are protected if the plans change. That makes the contract terms in Richland Parish worth watching, because other states will compare their own deals to what Louisiana decides.

Sources

•       The Center Square: Meta and Entergy power deal for the Richland Parish data center

•       Fortune: Democrats, AI data centers and electricity costs

•       Louisiana Illuminator: Meta's data center ownership transfer doesn't concern Louisiana power regulators

•       Office of Sen. Bernie Sanders: AI Data Center Moratorium Act announcement

•       Alliance for Affordable Energy and Union of Concerned Scientists: Motion for investigation, Louisiana PSC Docket U-37425 (advocacy groups quoting Entergy's filings)

•       The Advocate: Entergy makes case for expanding Meta data center in hearing while opponents question costs

•       WBRZ: Protest in Baton Rouge against proposal for new plants to power Meta Richland Parish data center

•       CleanTechnica: Louisiana Communities Rally Against Meta Gas Expansion (reports Sierra Club's account)

Have a correction or tip? See our corrections policy or contact the newsroom.