Meta's Richland Parish data center needs 7 gas plants lasting 30 years, but the deal lasts 15 to 20. Who pays the rest?
Meta plans to build one of the largest data centers in the world in Richland Parish, a farm parish of about 20,000 people. The project would require a large amount of power. Some reports put the need at 4,500 megawatts. That is about four times the demand of New Orleans.
To serve it, Entergy Louisiana proposes to build seven new gas plants. The proposal drew protesters to Baton Rouge. They asked the Louisiana Public Service Commission to reject the plan. Their concerns centered on two issues: cost and land.
Entergy says Meta will pay its full and fair share. Meta says it pays the full cost of the power it uses. Meta says the deal will save customers 2.65 billion dollars over 20 years.
The Dispute Turns on Time
A 30 Year Asset and a 15 Year Deal
The plants would last about 30 years. The deal with Meta would last about 15 to 20 years. That gap creates a well known problem in utility regulation. When an asset lives longer than the contract that justified it, the remaining cost does not disappear. It can become a stranded cost, and it often falls on the customers who remain on the system.
Public Service Commissioner Davante Lewis raised that point at the protest. He said he has not found comfort that home customers are safe from extra costs. He said if Meta does not renew, the stranded costs go back to home customers. In practical terms, the plant remains. The bill remains. The customer can leave.
What Meta Pays, and What It Does Not
The current structure reflects that risk. Meta is set to pay for about half the cost to build the plants over 15 years. That is what consumer advocates told the Associated Press. Meta is not set to pay for upkeep and daily work on the plants. And all grid users are set to help pay for a 550 million dollar transmission line to serve the site.
Four Issues Beyond the Power Bill
Tax Treatment
A second issue is tax treatment. Meta is exempt from sales tax under a 2024 state law. The state says that could cost tens of millions of dollars or more each year in lost funds. The public does not recover that money. It is simply not collected.
Disclosure
A third issue is disclosure. Key parts of the Meta and Entergy deal are under nondisclosure pacts. Regulators saw the deal. They could not share the facts. The result is an information gap. The people who would carry the long-term risk cannot fully review the terms that create it.
Land and Eminent Domain
A fourth issue is land. Entergy is in court to force owners of 14 tracts in Lincoln Parish to give up rights for a transmission line to feed the Meta site. One landowner at the protest, Sarah Bailey, said her great-grandmother bought the land for the family. Now the family must hire lawyers to keep it. The case raises a basic question about eminent domain: when a public tool is used to secure land for a line that serves one private customer, what limits apply?
If Meta leaves, its power use leaves too. That part is clear. But the bill for the plants does not leave. The line does not leave. The debt does not leave. The question is who pays for what remains.
An Alternative Already in Use
Bring Your Own Power
One alternative is already in use in other states. It is called bring your own power. The data center builds power at or near the site. It uses that power on site. It does not run it through the public grid first.
About one-fourth of planned United States data center capacity as of mid 2026 had some form of behind-the-meter power.
Amazon, Microsoft, and Oracle are among the firms that use it. Meta has moved that way in other places too. It has put billions toward its own power.
How the Risk Changes
Under that model, the risk allocation changes. If the data center closes in year 16, the firm owns an unused plant. There is no shared line bill. There is no claim that a utility needs public power to take land for a private firm. There is no rate base question.
That model does not resolve every issue. A company owned gas plant still burns gas. It does not resolve traffic, water use, or rent. It resolves one specific question: who pays if the project ends early. Under the current proposal, that risk sits largely with the public. Under a behind-the-meter model, it sits with the firm that requested the power.
What the Commission Decides in December
The Public Service Commission votes in December. Three broad paths are on the table. The Commission could approve the current version. It could require the contract term to match the life of the plants, or require upfront payment to cover the risk of early exit. Or it could reject this version and direct the parties toward a behind-the-meter structure.
The core issue is not whether the plant should be built. The core issue is contract design. When a 30-year asset is justified by a 15 to 20 year deal, someone must cover the remaining years. The December vote will decide who that someone is.
Sources:
WBRZ, Protest in Baton Rouge against proposal for new plants to power Meta Richland Parish data center
Louisiana First News, Protesters urge Louisiana regulators to reject Entergy plan for Meta data center, Nov. 19, 2026
Associated Press via TechXplore, Louisiana's $3B power upgrade for Meta project raises questions about who should foot the bill, Sept. 25, 2025
Baton Rouge Business Report, Legal challenge threatens Louisiana's data center fast track
Baton Rouge Business Report, Why the bring-your-own-power model is catching on with data centers